7th Avenue & 15th Street South Connection

15th & 7th 7-11-22

Project Update

The contractors have completed all the work on this project and it has been opened to all traffic. 

Project Milestones


PHASE 1 - Original Work 



STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
 All water main and sanitary sewer main utilities were installed.


Detention pond, drainage channel, and storm sewer installed. 


Placing gravel base course


Concrete curb and gutter and sidewalks. 


Asphalt paving



Backfill disturbed areas with topsoil and seed. 




PHASE 2 - Work at 7th Avenue and Remington Circle




STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
 • 
Reclaim roadway between the intersection of Remington Circle at 7th Ave north to original project limits

 
Install storm sewer


Install ramps


.Paving with asphalt






Project Overview:

This project is a new street construction project to connect 15th St. S. and 7th Ave S. at their intersection. The construction began in 2021 and will be finished in the summer of 2022. 

Completion Date:

Early August.

Contract Amount

$2,628,516.46

Contractor Name

Bowes Construction

Contractor Contact Information

Cole Schneider, Project Manager

605-693-3557

Contact Information

Jason Petersen

605-696-3200

JPetersen@civildes.com

Consultant Name

Civil Design Inc. (CDI)