8th Street South & Main Avenue Intersection Reconstruction

8th St. S. and main Completed

Project Update

The Contractors have completed all the work associated with this intersection, and the intersection is completely open to traffic. 

Route/Detour Information

There are no longer any detours related to this project. 

Project Milestones


STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
 Remove existing pavement within the intersection


Install new water main through the intersection


Backfill and prep the gravel base course


Install new concrete paving through the intersection & patch asphalt


Complete all the pavement markings and open the intersection to traffic. 


Project Overview:

This project entails the reconstruction of the street surface in the intersection as well as some sidewalk ramp and traffic signal upgrades. 

Completion Date:

August 5, 2022

Contract Amount

$612,000

Contractor Name

Bowes Construction

Contractor Contact Information

Cole Schneider, Project Manager

605-693-3557

Consultant Name

Civil Design Inc. (CDI)

Andrew Kangas, PE, LS

(605) 696-3200