8th Street South Mill and Overlay

8th St. S. 8-30-22

Project Update

The contractors have finished all the work for this project and the road has been reopened to all traffic. 

Project Milestones


STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
 Milling of the street surface


Adjusting manholes and water valves and prepping the street surface


Repaving the street. This may require lane closures or flaggers


Paint new road markings and bike lane markings


Project Overview:

Mill and Overlay 8th St. S. from Main Avenue to Medary Avenue

Completion Date:

End of August 2022

Contract Amount

$115,000

Contractor Name

Bowes Construction

Contractor Contact Information

Cole Schneider

605-693-3557

City Contact Information

Charlie Richter, City Engineer

605-629-6629